Welcome to BHEL PSER's Internet Site
new Recruitment of experienced graduate engineers and diploma holders (Civil) on fixed tenure basis.

Milestones Achieved 2021-2022
  • BRBCL Nabinagar Unit-4 (250 MW) --> Boiler Safety valves setting & floating have been completed successfully on 24/10/2021.new

  • RRVUNL Suratgarh Unit-8 (660 MW) --> Reliability Operation spread over a period of 30 days at various loads has been completed from 19/09/2021 to 23/10/2021.new

  • RRVUNL Suratgarh Unit-8 (660 MW) --> 72 hrs Trial Run completed on 06/10/2021 at 11:00 PM. COD declared from 00:00 hrs of 07/10/2021.

  • WBPDCL Sagardighi Unit-5 (660 MW) --> Chimney works started after the puja ceremony on 24/09/2021.

  • NTPC Barauni Unit-9 (250 MW) --> Generator Transformer has been made ready for synchronisation with in 55 days from its diversion from Uchahar site with completion of full erection and Commissioning cycle of GT with in this period. Unit 9 has been synchronised with this GT on 22/09/2021 at 21:17 HRS and is presently running at 231.4 MW

  • BRBCL Nabinagar Unit-4 (250 MW) --> Unit has been synchronized for the first time at 10:45 hrs on 20/09/2021.

  • Maitree Bangladesh Unit-2 (660 MW) --> Generator stator has been lifted successfully on 07/09/2021.

  • NSPCL Rourkela (250 MW) --> Unit synchronized successfully for the first time on 06/09/2021 at 18:32 hrs.

  • NSPCL Rourkela (250 MW) --> Boiler Light Up for synchronization has been done at 20:08 hrs on 31/08/2021.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> Full load achieved at 13:30 hrs on 30/08/2021.

  • BRBCL Nabinagar Unit-4 (250 MW) --> TG put on Barring Gear on 24/08/2021 at 19:45 hrs in the presence of CEO BRBCL/NTPC and other senior officials of BRBCL and BHEL.

  • The article published in "The Bhutanese" on 21/08/2021 titled “BHEL Races against Time to Restore Unit#3 of Mangdechhu Hydroelectric Project”.

  • Mangdechhu HEP Unit-3 (180 MW) --> The restoration activity is in final stage. Mechanical spinning has been completed successfully on 14/08/2021 at rated speed of 375 RPM.

  • Mangdechhu HEP Unit-3 (180 MW) --> Generator stator Restoration Job : Generator Stator has been lowered successfully on 25/07/2021. Total weight of the Stator is 245 MT.

  • NPGCL Nabinagar Unit-2 (660 MW) --> COD has been formally declared at 00:00 hrs on 23/07/2021 in a virtual ceremony organised at NPGCL in the august presence of Director (Operations - NTPC) / Chairman, NPGCL Director (Projects) - NTPC, Director (Power & HR) - BHEL, ED (PSER), ED (PSTS) & other dignitaries of NTPC & BHEL.

  • BRBCL Nabinagar Unit-4 (250 MW) --> Steam Blowing started on 23/07/2021 with test blow at 25 kg per sq cm.

  • Mangdechhu HEP Unit-3 (180 MW) --> Final HV test of stator @ 28.60 KV has been completed successfully on 21/07/2021.

  • WBPDCL Sagardighi Unit-5 (660 MW)--> ESP mechanical erection started on 05/07/2021 in the presence of Director (Projects)/WBPDCL and Director (O&M)/WBPDCL.

  • Punatsangchhu-II Unit-2 (170 MW) --> Core Flux and Hot Spot test of Generator Stator has been completed successfully on 26/06/2021. Core losses observed within permissible limit and no Hot spot detected during the test.

  • Punatsangchhu-II Unit-1 (170 MW) --> Hydro test of Spiral casing is successfully completed on 19/06/2021. Hydro test pressure is 53.4 kg per sq cm.


Power Sector-Eastern Region (PSER) of Bharat Heavy Electricals Limited, is the Eastern Wing of the Company's Power Sector, with its head office at Kolkata, catering its services to the eastern part of India. The states which are being covered are Bihar, Jharkhand, Chhattisgarh, Odisha, West Bengal, Assam, Manipur, Meghalaya, Mizoram, Arunachal Pradesh, Nagaland, Tripura and Sikkim. Apart from the above, PSER has crossed the barrier of conventional boundaries and is executing projects in the states of Andhra Pradesh, Telengana and Rajasthan as well. Add to that projects are also being executed outside India. The Service group is engaged in overhauling and trouble shooting of different technical problems of power stations.

OUR CUSTOMERS:   CSEB   DVC   NTPC   BRBCL   WBPDCL   DPL   KBUNL   HNPCL   BSEB   SCCL   RVUNL   OPGCL   OTPC   ABHIJIT   APNRL   TSPCL   CSPGCL   APGCL   TATA POWER   NEEPCO   IOCL   IISCO   BRPL   OIL   BCPL   NHPC   NPGCL   BIFPCL