Welcome to BHEL PSER's Internet Site

Milestones Achieved 2021-2022
  • BRBCL Nabinagar Unit-4 (250 MW) --> Commercial Operation Declaration (COD) has been done w.e.f 00:00 hrs of 01/12/2021.new

  • BRBCL Nabinagar FGD Package (4 x 250 MW) --> Casting of 1st Segment of Unit-1 Chimney done on 06/12/2021.new

  • BRBCL Nabinagar Unit-4 (250 MW) --> 72 hours Trial Operation for COD has been successfully completed at 22:30 hrs on 10/11/2021. It is the first NTPC Unit to achieve this in a minimum period of 11 days from first-time Full Load achievement.

  • BRBCL Nabinagar Unit-4 (250 MW) --> 72 hrs Full Load Trial Operation is under progress from 09:00 hrs on 07/11/2021 and to be continued till 09:00 hrs on 10/11/2021, prior to Commercial Operation Declaration (COD).

  • Punatsangchhu-II Unit-2 (170 MW) --> Spiral Casing has been successfully on 06/11/2021 with Hydro Test pressure of 53.4 kg per sq cm.

  • Maitree Bangladesh (2 x 660 MW) --> Auxiliary Boiler light up successfully done on 31/10/2021 at 20:00 hrs BST.

  • BRBCL Nabinagar Unit-4 (250 MW) --> Full load achieved at 01:15 hrs on 30/10/2021.

  • NTPC Barh Unit-1 (660 MW) --> Trial operation declared successfully completed at 00.00 hrs of 30/10/2021.

  • NTPC Barauni Unit-9 (250 MW) --> Commercial Operation declared w.e.f 00:00 hrs of 01/11/2021.

  • BRBCL Nabinagar Unit-4 (250 MW) --> Unit has been synchronized at 04:34 hrs on 28/10/2021 and Coal firing started (Mill-A taken in service).

  • BRBCL Nabinagar Unit-4 (250 MW) --> Boiler Safety valves setting & floating have been completed successfully on 24/10/2021.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> Reliability Operation spread over a period of 30 days at various loads has been completed from 19/09/2021 to 23/10/2021.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> 72 hrs Trial Run completed on 06/10/2021 at 11:00 PM. COD declared from 00:00 hrs of 07/10/2021.

  • WBPDCL Sagardighi Unit-5 (660 MW) --> Chimney works started after the puja ceremony on 24/09/2021.

  • NTPC Barauni Unit-9 (250 MW) --> Generator Transformer has been made ready for synchronisation with in 55 days from its diversion from Uchahar site with completion of full erection and Commissioning cycle of GT with in this period. Unit 9 has been synchronised with this GT on 22/09/2021 at 21:17 HRS and is presently running at 231.4 MW

  • BRBCL Nabinagar Unit-4 (250 MW) --> Unit has been synchronized for the first time at 10:45 hrs on 20/09/2021.

  • Maitree Bangladesh Unit-2 (660 MW) --> Generator stator has been lifted successfully on 07/09/2021.

  • NSPCL Rourkela (250 MW) --> Unit synchronized successfully for the first time on 06/09/2021 at 18:32 hrs.

  • NSPCL Rourkela (250 MW) --> Boiler Light Up for synchronization has been done at 20:08 hrs on 31/08/2021.

  • RRVUNL Suratgarh Unit-8 (660 MW) --> Full load achieved at 13:30 hrs on 30/08/2021.


Power Sector-Eastern Region (PSER) of Bharat Heavy Electricals Limited, is the Eastern Wing of the Company's Power Sector, with its head office at Kolkata, catering its services to the eastern part of India. The states which are being covered are Bihar, Jharkhand, Chhattisgarh, Odisha, West Bengal, Assam, Manipur, Meghalaya, Mizoram, Arunachal Pradesh, Nagaland, Tripura and Sikkim. Apart from the above, PSER has crossed the barrier of conventional boundaries and is executing projects in the states of Andhra Pradesh, Telengana and Rajasthan as well. Add to that projects are also being executed outside India. The Service group is engaged in overhauling and trouble shooting of different technical problems of power stations.